In an AON graph of a project, there only exists one path from the first to the last activity.

Group startsTrue or False

True, unselectedbutton,In unavailable

Falseselected button,unavailable

 

 

Conceptual Question 19-14 The key objectives of a project are given…

The key objectives of a project are given by

 

multiple choice

  • time, scope, and budget.
  • cost, Quality, and location.
  • customers, suppliers, and employees.

efficiency, effectiveness, and success.

 

 

Conceptual Question 19-2 Consider the simple dependency…

Consider the following, simple dependency matrix.

 

Simple dependency

matrix   Predecessor

activity

A1        A2

Successor

activity        A1

A2        X

 

 

Which of the following statements is ?

 

multiple choice

  • The two activities are independent of each other and the project can carry out both of them immediately.
  • A1 is a predecessor activity to A2.
  • A2 is a predecessor activity to A1.

None of these statements is .

 

 

 

The key objectives of a project can be summarized in the form of a

 

multiple choice

  • line.
  • triangle.
  • square.

hexagon.

 

 

 

Which of the following statements is  with respect to a Gantt chart?

 

multiple choice

  • The x-axis of a Gantt chart shows a time line.
  • The y-axis shows the activities of a project.
  • The Gantt chart itself does not show all dependencies among activities.
  • The Gantt chart is named after 19th-century industrialist Henry Gantt.
  • All of these statements are .

 

 

 

Which of the following statements is  with respect to slack time?

 

multiple choice

  • The slack time of an activity is the latest completion time of the activity minus the earliest completion time.
  • The slack time of an activity is the latest start time of the activity minus the earliest start time.
  • The slack time of an activity determines how long an activity can be delayed without impacting the overall completion of the project.
  • All of these statements are .

 

 

 

Which of the following statements is  with respect to an AON graph of a project?

 

multiple choice

  • In an AON graph, the activities are on the edges of a graph.
  • In an AON graph, the activities are on the nodes of a graph.
  • AON stands for the American Operations Norm.

None of these statements is .

 

 

A project has four activities that take 4, 3, 6, and 7 days, respectively. What is the total completion time for the project?

 

multiple choice

  • 3 days, because this is the minimum time
  • 7 days, because this is the maximum time
  • 20 days, because this is the sum of the times
  • It is not possible to determine the total completion time from the given information

 

 

Conceptual Question 19-3 Consider a project with two activities that…

Consider a project with two activities that are interdependent. Which of the following statements is ?

 

multiple choice

  • Both activities can be carried out in parallel without coordination.
  • Static coordination of the two activities implies that the two activities are carried out in an iterative manner.
  • Dynamic coordination of the two activities implies that the two activities are carried out in an iterative manner.

None of these statements is .

 

 

 

Consider two projects that have the same activities and the same dependencies. In the first project, the activity times are expected outcomes. The actual times will vary. In the second project, the activity times are always as expected. Assuming the expected activity times are identical across the two projects, which project will be completed first?

 

multiple choice

  • The first
  • The second

Cannot be determined