OPS 571 Wk 3 – Apply: Week 3 Exam

0 items
OPS 571 Wk 3 – Apply: Week 3 Exam
OPS 571 Wk 3 – Apply: Week 3 Exam
$20.00
  • Description

OPS 571 Wk 3 – Apply: Week 3 Exam

Complete the Week 3 Exam in McGraw-Hill Connect.

 

Dr. Eli Goldratt feels that the goal of a firm is to make useful products efficiently.

 

 

 

An activity where the parts that go into each unit of a product are periodically removed from inventory and accounted for based on the number of units produced is called which of the following?

Multiple Choice

Frozen window

Backflush

Level schedule

Group technology

Kanban

 

 

Smaller transfer batches give lower work-in-process inventory and faster product flow.

 

JIT production means that we produce the product before it is required so the customer does not wait for the product.

 

 

Group technology is a philosophy wherein similar parts are grouped together and the processes required to make the parts are arranged as a work cell.

 

 

According to the theory of constraints, which of the following is a financial measurement that can be used to measure the firm’s ability to make money?

Multiple Choice

Net profit

Throughput

Inventory

Sales

Retained earnings

 

 

 

Which of the following are related to lean production?

Multiple Choice

A philosophy of waste elimination

Lean consumption

Never running out of inventory

TheWahei-Subaru method

Full use of capacity

 

Preventive maintenance is emphasized in lean production to ensure that flows are not interrupted by downtime or malfunctioning equipment.

 

 

According to the theory of constraints, a non-bottleneck is any resource where capacity is less than the demand placed on it.

 

 

The effects of statistical variations in processing times in a dependent sequence will eventually cancel themselves out due to the law of averages.

 

 

You have been called in as a consultant to set up a kanban control system. The first thing you do is to determine the number of kanban card sets needed. Your research shows that the expected demand during lead time for a particular component is 1,200 per hour. You estimate the safety stock should be set at 5 percent of the demand during lead time. The tote trays used as containers can hold 2 units of stock, and the lead time to replenish an order is 10 hours. Which of the following is the number of kanban card sets necessary to support this situation?

Multiple Choice

5,000

5,500

6,300

6,500

7,000

 

 

In setting up a kanban control system you need to determine the number of kanban card sets needed. If the expected demand during lead time is 25 per hour, the safety stock is 20 percent of the demand during lead time, the container size is 5, and the lead time to replenish an order is 5 hours, what the number of kanban card sets is needed?

Multiple Choice

5

20

27

30

34

 

 

In setting up a Kanban control system you need to determine the number of kanban card sets needed. If assume the expected demand during lead time is 50 per hour, the safety stock is 20 percent of the demand during lead time, the container size is 4, and the lead time to replenish an order is 8 hours, what number of Kanban card sets is needed?

Multiple Choice

60

80

90

120

150

 

 

 

Looking at the loads that are placed on each resource by the products that are scheduled through them is called process flow profiling.

 

 

following is not listed in the textbook as a component of a lean supply chain?

Multiple Choice

Lean customers

Lean management

Lean logistics

Lean warehousing

Lean procurement

 

 

 

Which of the following is an element that addresses elimination of waste under lean production?

Multiple Choice

Production ahead of demand

Group plant loading technology

Kanban production control system

Minimized run times

Full capacity utilization

 

 

Lean production is an integrated set of activities designed to achieve high-volume production using minimal inventories of raw materials, work-in-process, and finished goods.

 

 

The term “dependent events” refers to a process sequence.

 

 

Subcontractor networks are not very important in Japanese manufacturing.

 

According to the theory of constraints, a bottleneck is any resource whose capacity is greater than the demand placed on it.

 

From an operations standpoint, one of the goals of the firm under the theory of constraints is to increase throughput while simultaneously reducing inventory and reducing operating expense.

 

 

Which of the following address elimination of waste under lean production?

Multiple Choice

Info-matic warehouse networks

Outsourced housekeeping

Quality at the source

Backflush

Bottom-round management

 

 

A way to find a bottleneck is to use one’s knowledge of a particular plant, look at the system in operation, and talk with supervisors and workers.

 

 

In the textbook, Toyota’s Fujio Cho identified which of the following types of waste to be eliminated?

Multiple Choice

Underproduction

Excess quality

Preventive maintenance

Product defects

Kaizen

 

 

Lean production requires a “push and pull” system of inventory replenishment.