Complete the Week 4 Practice: Project Management Quiz in McGraw-Hill Connect.

 

The following table represents a plan for a project:

 

TIMES (DAYS)

JOB NO. PREDECESSOR

JOB(S)   a      m    b

1     –     2     3     4

2     1     1     2     3

3     1     4     5     12

4     1     3     4     11

5     2     1     3     5

6     3     1     2     3

7     4     1     8     9

8     5, 6  2     4     6

9     8     2     4     12

10    7     3     4     5

11    9, 10       5     7     8

________________________________________

 

  1. Indicate the critical path.

1-3-6-8-9-11

1-2-5-8-9-11

1-4-7-10-11

 

 

 

  1. What is the expected completion time for the project? (Do not round intermediate calculations. Round your answer to 2 decimal places.)

 

 

  1. You can accomplish any one of the following at an additional cost of $1,500. If you will save $1,000 for each day that the earliest completion time is reduced, which of the following actions should be taken, if any?

 

  1. Reduce job 5 by two days.

Yes

No

 

 

  1. Reduce job 3 by two days.

Yes

No

 

  1. Reduce job 7 by two days.

Yes

No

 

 

  1. What is the probability that the project will take more than 30 days to complete? (Use Excel’s NORMSDIST() function to find the correct probability for your computed Z-value. Other than the expected completion time you entered in part c above, do not round intermediate calculations. Round “z” value to 2 decimal places your final answer to 4 decimal places.)

 

 

 

There is an 82 percent chance the project below can be completed in X weeks or less.

 

ACTIVITY     MOST OPTIMISTIC     MOST

LIKELY  MOST PESSIMISTIC

A     2     5     11

B     3     3     3

C     1     3     5

D     6     8     10

E     4     7     10

________________________________________

 

What is X? (Do not round intermediate calculations. Round your answer to the nearest whole number.)

 

 

 

The following represents a project that should be scheduled using CPM:

 

TIMES (DAYS)

ACTIVITY     IMMEDIATE PREDECESSORS  a      m    b

A     —    1     3     5

B     —    1     2     3

C     A     1     2     3

D     A     2     3     4

E     B     3     4     11

F     C, D       3     4     5

G     D, E       1     4     6

H     F, G 2     4     5

________________________________________

 

 

  1. What is the critical path?

A-D-F-H

A-C-F-H

B-E-G-H

A-D-G-H

 

 

  1. What is the expected project completion time? (Do not round intermediate calculations. Round your answer to 2 decimal places.)

 

 

  1. What is the probability of completing this project within 16 days? (Use Excel’s NORMSDIST() function to find the correct probability for your computed Z-value. Do not round intermediate calculations. Round “z” value to 2 decimal places and final answer to 4 decimal places.)

 

 

What type of chart compares the current project schedule with the original baseline schedule so that deviations from the original plan can be easily noticed?

Multiple Choice

Project calendar

Project task tree

Milestone chart

Tracking Gantt chart

Bar chart

 

 

 

In a Gantt chart, the horizontal axis is usually which of the following?

Multiple Choice

Activities

Cost

Profit

Time

Milestones

 

 

You have just been assigned to oversee a series of projects. Functional areas will loan you personnel for each project, and separate project managers will be responsible for separate projects. These project managers will report to you. Which project management structure is being used?

Multiple Choice

Pure project

Task force

Matrix project

Functional project

PERT

 

 

 

You have just performed a CPM analysis and have found that more than one path through the project network has zero slack values. What can you conclude?

Multiple Choice

You have incorrectly performed the analysis.

You have multiple critical paths.

Only one path is optimal.

More than one path is optimal.

The project will not be completed by the desired time.

 

 

A simple project listing of five activities and their respective time estimates are presented here:

 

 

Using CPM, which activities make up the critical path?

Multiple Choice

A, C, D, E

A, B, D, E

A, C, B, D, E

A, D, E

None of these

 

 

You are looking at a chart that has the terms BCWS, BCWP, and AC indicating lines on the chart. What kind of chart are you looking at?

Multiple Choice

Gantt chart

PERT chart

Bar/milestone chart

Total program cost breakdown

EVM chart

 

 

Popular project management software used in mid-sized projects is

Multiple Choice

Microsoft Word.

Microsoft Primavera.

Microsoft Project.

Microsoft Excel.

None of these